Loudoun County pauses data center approvals while it rewrites its rules
The Northern Virginia county, home to about 245 data center buildings, voted 7-1-1 to hold Board votes on data center and substation applications until new standards are finished, expected in July 2027.
- → Loudoun's Board of Supervisors voted 7-1-1 on November 17 to pause action on legislative data center and substation applications, effective as of September 15 1.
- → The pause runs until Phase 2 of the county's Data Center Standards and Locations project is finished, expected in July 2027 1.
- → County staff count 33 active legislative applications for data centers and substations, most of which could be affected 1.
- → By-right administrative approvals, including grandfathered projects, are not covered; the county attorney said the Board lacks authority to pause them 1.
Loudoun County, Virginia, the largest data center market in the US, has stopped advancing new data center and substation rezonings and special exceptions to final votes while it writes tougher development standards. The Board of Supervisors voted 7-1-1 on Tuesday, November 17, to adopt the formal resolution, which is effective as of September 15 1.
The county says about 245 data center buildings are built or under construction there, totaling around 58 million square feet, and another 55 million square feet has been approved or is in review 1. Commercial Observer reported that the facilities generate about $1.3 billion a year in local tax revenue 2.
What the pause covers
Developers can still file applications, and county staff and the Planning Commission can keep reviewing them. But paused applications generally will not go to the Board for a public hearing or final vote until Phase 2 of the Data Center Standards and Locations initiative is complete, which the county expects in July 2027 1. Applicants will then be expected to revise their plans to meet the new rules. Substations that qualify as grid reliability substations are exempt but still need Board approval 1.
County staff count 33 active legislative applications for data centers and substations, "the vast majority" of which could be affected 1. Under Virginia law the Board has 12 months after an application's Planning Commission hearing to act unless the applicant agrees to an extension. At least nine applications are expected to hit that deadline before Phase 2 ends; staff will ask those applicants to defer voluntarily, and applications can reach the Board earlier if they decline 1.
The pause does not reach by-right administrative applications, including projects grandfathered under the county's 2025 Data Center Grandfathering Resolution. The County Attorney's Office concluded the Board has no authority for a broader moratorium on those 1.
What comes next
Phase 1 of the initiative, finished in March 2025, largely ended by-right data center development and required new proposals to seek a special exception 1. Phase 2 is looking at limits on where data centers and substations can go, including distance from homes and schools, along with rules on building height, noise and on-site power generation 1. Developers argued the delay would hurt investor confidence and disrupt projects planned under existing rules, and the measure could face legal challenges, Commercial Observer reported 2. Nearby Prince William County tightened its data center zoning in September, and Montgomery County, Maryland, adopted an 18-month freeze in July 2.