DeSoto County rejects two rezonings for a gas-powered data center complex
Florida commissioners turned down DCIP Group's 238-acre rezoning in a 2-2 tie on October 27 and rejected a second, larger application the next day.
- → A rezoning of about 238 acres for a hyperscale data center failed 2-2 on October 27 after one commissioner recused himself 1.
- → A second DCIP application, covering a 554-acre property planned for nine facilities and 2.1 million square feet, failed on October 28 2.
- → The planning commission had recommended denial of the second application 4-1 earlier in October 1.
- → The county rezoned 34 acres at a former power plant site in March and adopted a one-year data center moratorium in July 1,2.
DeSoto County commissioners in southwest Florida rejected two rezoning applications from DCIP Group on consecutive days in late October, stopping, for now, the developer's plan for a complex of natural gas-powered data centers near Arcadia 1,2.
On Tuesday, October 27, after a six-hour meeting, a request to rezone about 238 acres for a hyperscale data center failed on a 2-2 tie. Commissioner Steve Hickox recused himself over a potential conflict of interest 1. On Wednesday, October 28, a second application covering a larger assembly of land failed, with commissioners splitting along the same lines 2.
What was proposed
According to a county staff report, DCIP planned nine facilities totaling 2.1 million square feet on a 554-acre property, and sought more than 15 facilities in the county in all 2. The company said the buildings would not draw from the local grid and would instead run on natural gas, with power generated on a 34-acre site at a decommissioned power plant on Roan Street that the county rezoned in March 1,2. DCIP's team said required permits would include air, protected species and industrial wastewater approvals, and that it had not sought economic incentives 1.
The planning commission voted 4-1 earlier in October to recommend denial of the second application 1. Planning Director Misty Servia told commissioners the project did not fit the Arcadia urban area expansion plan, that no information had been provided on industrial wastewater disposal, and that the county has no data center regulations against which to judge it 1,2. Staff proposed conditions in case of approval, including a one-story height limit and 25% open space 1.
Noise and the vote
An acoustics expert recommended a 45 dBA noise limit; DCIP's consultant proposed 55 dBA and a complaint-based process instead of continuous monitoring 1. Commissioner Elton Langford called the project "a good deal" for tax revenue, and Commissioner J.C. Deriso said it could have a "lasting, positive impact" 1,2. Commissioner Judy Schafer called it "too massive," and Commissioner Jerod Gross said, "I don't feel that it's the right place" 1,2.
The county adopted a one-year moratorium on new data center applications in July, which covers new filings while it has no data center rules 1,2. Reports on the votes did not say what DCIP plans next for the rejected sites; the company's chief executive declined to comment after the first meeting 1.
- WGCU / Suncoast Searchlight: DeSoto County rejects data center rezoning with another vote ahead
- WUSF: DeSoto data center proposal is blocked again