Spartanburg County approves three data center deals while its moratorium stays in place

Council gave final approval to three development agreements worth about $5.5 billion on November 16 and sent three more AIB projects at Tyger River Industrial Park to further readings.

PermitQuant · 24 November 2026

Spartanburg County Council in South Carolina gave final approval on Monday, November 16, to development agreements for three data center projects and advanced three more, even as the county's data center moratorium remains in force 1,2.

The approved agreements cover a Valara Holdings project at 4000 South Pine Street, described as a 457 MW facility with about $2.76 billion of investment; a project of up to 65 MW of IT capacity on about 137 acres at or near 430 Jones Road, valued at about $1.5 billion; and AIB Data Centers' CLT1, a 50 MW, roughly $1.2 billion conversion of a former bitcoin mining facility at 389 Tyger River Industrial Drive 1. Fox Carolina reported that construction has already started at the South Pine Street site, which it attributed to developer Northmark, and that CLT1 now moves to permitting 2.

Data center agreements before Spartanburg County Council, November 16, 2026
ProjectLocationCapacityStated investmentStatus
Valara4000 South Pine Street457 MWAbout $2.76 billionFinal approval
Jones Road430 Jones Road (about 137 acres)Up to 65 MW ITAbout $1.5 billionFinal approval
AIB CLT1389 Tyger River Industrial Drive50 MWAbout $1.2 billionFinal approval
AIB CLT2-CLT4Tyger River Industrial Park65 MW, 50 MW, 50 MWAbout $6.9 billion combinedFirst reading
Source: [1]

How projects are moving during the moratorium

The county adopted a data center moratorium in September. It includes an exception that lets data centers of 65 MW or less proceed on designated industrial park sites or former industrial properties if they meet additional requirements 1. Projects have advanced through council-approved amendments that limit data centers to 65 MW and to industrial park sites, and the moratorium is due to expire in about 10 months 2.

The Jones Road site shows how that path works. County planning staff denied an earlier data center application there in June, citing violations of the Unified Land Management Ordinance, and the Board of Zoning Appeals upheld the denial on August 25. The developer is now pursuing the project under the moratorium exception and a development agreement instead 1. That agreement includes $9 million in community benefit payments over five years and 25 full-time jobs 1.

Three more projects at Tyger River

AIB's CLT2, CLT3 and CLT4 passed first reading. According to AIB, CLT2 would be 65 MW on one lot and CLT3 and CLT4 would be 50 MW each on a second lot, with combined investment of about $6.9 billion and $39 million in development agreement payments over 15 years 2. AIB said those three would generate their own power with solid oxide fuel cells rather than draw from the grid, and that each project would use about 65,000 gallons of water a year 2. For CLT1, AIB cited $12.6 million in payments over 12 years and said it will run on grid power 2.

Each of the three needs two more readings, its own public hearing and a final council vote 2. At the meeting, opponents raised transparency, water supply, utility costs and noise; supporters cited investment and the reuse of industrial property 2. A separate 400 MW campus proposed at the same industrial park earlier this year, Project Spero, was rejected by council and later withdrawn, according to AIB 2.

Spartanburg CountySouth CarolinaData centersDevelopment agreementsMoratorium
Sources
  1. Fox Carolina: Spartanburg County council takes up 6 data center development agreements Monday
  2. Fox Carolina: Spartanburg Co. Council gives final approval to 3 data center agreements, advances 3 more
More news
Policy · 24 Nov

Senate passes permitting bill that would shorten federal reviews for housing projects

Policy · 24 Nov

Voters approve state housing bonds but reject looser lot-size and review rules

Policy · 24 Nov

DeSoto County rejects two rezonings for a gas-powered data center complex

Data · 24 Nov

A 1,458-unit Hudson Yards tower tops NYC's new building filings of the past year